Key points for practical calibration of AILEIKE 60MPa pressure transmitter (HART protocol)
Pressure transmitters (HART protocol) are applied in various industries, and instrument measurement deviations can affect their stability. To reduce performance issues caused by equipment aging, minimize overall measurement errors, and standardize on-site calibration, this article uses the AILEIKE ALKB9802 portable hydraulic pump as the pressure generator, the ALKC400T precision digital pressure gauge to provide pressure reference, and the ALK475TREX (Chinese version) HART handheld device to complete HART instrument debugging. Prior to the operation, environmental pretreatment and instrument wiring verification should be carried out. A step-by-step pressure increase and decrease method is used to conduct multi-point testing, collecting and recording pressure and current output values at each point. Calibration of zero and range parameters, as well as verification of instrument return difference and output, are also performed. During operation, pressure is slowly increased and decreased, and readings are recorded after the pressure stabilizes, ensuring long-term stable and accurate monitoring by the transmitter.
1. Calibration tool for pressure transmitter (HART protocol)

The entire verification process must strictly adhere to the current metrological technical specifications. The main references include: JJG 882-2019 "Pressure Transmitter", which is applicable to the verification, periodic calibration, and in-service inspection of pressure transmitters. It is used to standardize the verification of the transmitter's indication error, hysteresis, and repeatability.
II. Detailed Explanation of Operational Procedures
(I) Preliminary preparations
1. Environmental requirements
The temperature should be controlled at (20±2)℃, with a relative humidity of ≤85%RH, and there should be no condensation. Ensure that the site is free from vibration, dust, and corrosive gases.
2. Hydraulic pump injection and pressurization for conduction
• Prepare the pressure transmission medium (pure water or calibration oil) and a syringe.
First, unscrew the exhaust knob on the ALKB9802 liquid storage cup. Use a syringe to draw up the medium and inject it into the storage cup. Ensure that enough medium is injected (no less than two-thirds of the cup). After the injection is complete, tighten the knob securely.
• Next, discharge the excess gas from the hydraulic pump. First, unscrew the plugs from the two output ports, then loosen the knob on the injection port, and open the stop valve (just loosen it half a turn). Adjust the micro-adjustment knob counterclockwise until it stops, and then close the pressure relief valve. Next, use the hand pressure lever to apply pressure, allowing the pilot pressure to reach the two output ports.
3. Tool connection
• Connect the pressure transmitter and the Precision digital pressure gauge alkc400T to the ALKB9802 output port seal.
• Wiring method 1 (precision digital pressure gauge powered by 24V):
(1) Wiring of the red test line: Insert one end into the 24V interface of the standard meter, and clamp the other end onto the positive terminal of the transmitter
(2) Connect the transmitter's negative terminal to a 250Ω resistor
(3) Black test wire wiring: Insert one end into the standard meter current interface, and clamp the other end onto one side of a 250Ω resistor
(4) Wiring of the handheld communicator communication cable: One end is plugged into the communication interface of the handheld communicator, and the other end is clamped to both ends of a 250Ω resistor
(5) Complete the wiring to form a closed circuit
Wiring diagram (I)
• Wiring method 2 (ALK475TREX handheld communicator 24V power supply):
(1) Connection of the red test wire: Insert one end into the current interface of the standard meter, and clamp the other end onto the negative terminal of the transmitter
(2) Black test line wiring: Insert one end into the standard meter's common terminal interface
(3) Wiring of the handheld communicator communication cable: Plug one end into the handheld communicator communication interface, clip the red clip onto the transmitter's positive terminal, and clip the black clip together with the clip of the black test cable
(4) Complete the wiring to form a closed circuit, and turn on the 24V switch power supply of the ALK475TREX handheld device
Wiring diagram (II)
• If the transmitter indicates a value other than 0 under current atmospheric pressure, and the standard meter measures a deviation in the transmitter's current value of 4mA, then take out the HART handheld device to calibrate the transmitter's zero point and current.
4. Specific calibration steps for the handheld device
(1) Calibrate the transmitter zero point
Turn on the power of the handheld device, and the handheld device has successfully communicated with the pressure transmitter

(2) Calibrate the transmitter current value measured by the pressure gauge to 4mA or 20mA
(II) Calibration process of pressure transmitter (HART protocol)
1. Voltage boost calibration process
• Use the hand pressure lever to gradually increase pressure clockwise, stopping when the pressure reaches approximately 5~10MPa. Close the stop valve, and then use fine adjustment to increase pressure clockwise to the verification point of 15MPa. If there is a deviation between the pressure value measured by the transmitter and 15MPa, and if the current value measured by the standard meter for the pressure transmitter is also 8mA, take out the handheld device to calibrate the pressure and current values.
• Calibrate transmitter pressure value:
Select low-range trimming or high-range trimming. When the pressure value measured by the transmitter is below 15MPa, select low-range trimming; when the pressure value is above 15MPa, select high-range trimming. Then press the right button, enter the pressure value of 15MPa, and finally press the right button to confirm. The pressure value and current value are calibrated successfully simultaneously.
• Then, directly use the fine adjustment to pressurize clockwise to the verification point of 30MPa. The current value should be 12mA. If there is a deviation between the pressure value of the transmitter and the current value measured by the standard meter, take out the handheld calibrator to calibrate the pressure and current values.
• For the same operation, directly use fine adjustment to pressurize to the verification points of 45MPa and 60MPa. The corresponding current values should be 16mA and 20mA, respectively. If there is an error, calibrate with a handheld device (as per the above operation).
2. Pressure reduction calibration process
• Use fine adjustment to reduce the pressure counterclockwise to a pressure value of 45MPa. The current value measured by the standard meter for the pressure sensor should be 16mA. If there is a deviation, the handheld device needs to be taken out to calibrate the pressure and current values.
• For the same operation, directly use the trimming to reduce the pressure to the verification points of 30MPa and 15MPa. The corresponding current values should be 12mA and 8mA. If there is an error, calibrate with a handheld device (as per the above operation).
Record the correspondence between pressure and current at each point, and verify whether the return difference (current difference at the same point during pressure increase and decrease) meets the requirement (≤0.05%FS).
3. Pressure relief process
Open the pressure relief valve and the stop valve, gradually release the pressure inside the pipeline until it reaches 0, and then the measurement is complete.
III. Precautions
Standardized use
• The pressure transmitting medium needs to be clean and free of impurities to prevent blockage of the pipeline and damage to the hydraulic pump and pressure gauge.
• Operations should follow standard procedures. The ALKB9802 portable hydraulic pump should be pressurized and depressurized slowly to avoid pressure shock.
• The wiring of the communication cable between the digital pressure tester ALKC400T and the handheld device must be clearly identified to prevent reverse connection.
• The readings at the verification points should be taken after the values on the standard gauge have stabilized, and the records should be kept accurate in real time.
• After the inspection is completed, slowly release the pressure to zero, ensuring there is no residual pressure. Turn off the equipment power supply before removing the inspected instrument.
Maintenance and calibration cycle
• Regularly conduct metrological verification on the digital pressure tester ALKC400T (it is recommended to do so once a year) to ensure that the measurement accuracy meets the standard.
• When the pressure gauge is not in use, the power should be turned off. If it is not used for a long time, it should be charged once every three months.
• If the hydraulic pump is not to be used for a long time, it should be depressurized before storage. Pour out the liquid in the reservoir cup and cover it with a cloth cover to prevent dust from entering the instrument.
IV. Conclusion
This set of calibrations maintains the stability of the pressure transmitter (HART protocol) through standardized operations, on-site environmental control, instrument connection, step pressure verification, test data recording, and other aspects. It corrects the indication deviation caused by zero point and range adjustments, completes the return difference and current 4~20mA output. The operation requirements are refined, and uniform pressure application, stable readings, and standardized wiring are implemented to prevent hidden dangers such as pressure damage to instruments and wiring errors. Regular calibration and maintenance are organized to reduce the risk of instrument failure and provide metrological support for precise adjustment in industrial production.